Ask the Manufacturing Execution Systems (MES) Expert: Scheduling Assistance
Asked on | Q | Dear Mr Amann,
In your opinion what are the lessons learned from the problems faced by Boeing 787 causing delivery postponing? Andre Iguti(2), SJC, NA |
| A | There are many factors in any situation like this, but some of the lessons learned have been: - When outsourcing design, you need to manage the suppliers, set expectations, and track performance. Do not just assume they will deliver as expected. Strong program management is essential.
- A very tight compression of development, assembly, test, and delivery cycles is prone to slip. You must have realistic margins, resources, and plans to address slips.
- Introduction of new methods, materials, and technologies will always be more complex than originally assumed. Add time and resources to deal with it.
|
|
|
|
|
|
|